2009
- Complete the new westbound lanes of I-90 and open to traffic by the end of July 2009.
Concrete paving is complete with work continuing on the asphalt shoulder.
Westbound lanes of I-90 tentatively scheduled to open to traffic on July 24. 2009.
- Complete grading and surfacing on SD79 from north Kimberly Drive to south Kimberly Drive.
- Grading and C&G are completed.
- Asphalt surfacing is scheduled to be completed by July 29, 2009
- Complete grading and surfacing on SD79 from Foothills Road (Old Exit 51 on and off ramp) to the Existing Eastbound I-90 bridge over the RR tracks.
- Grading is complete.
- Asphalt surfacing is scheduled to be completed by July 31, 2009.
- Begin construction of the new eastbound lanes of I-90 August 10, 2009.
- Traffic will be switched to two-way traffic in the newly constructed westbound lanes so the eastbound lanes can be constructed.
- Eastbound lanes of I-90 scheduled to be completed October 30, 2009.
- Complete grading and surfacing on SD79 between south Kimberly Drive and Anderson Road.
- Tentatively scheduled to start on August 17, 2009.
- Traffic will maintained on a gravel surface and piloted through the construction zone during working hours. During non-working hours one lane of traffic will be open both directions
|
|