Logo for the SDDOT
spacer graphic
SDDOT Header Graphic

Main Navigation
  General Information
  Const. Projects
  Doing Business
  Divisions
  Publications
  Traveler Information
  Vehicle Information

Construction Projects
  Chamberlain Truss
  Highway 85
   Belle Fourche
  I-90 Exit 30
  I-90 Exit 52
  Various SF
   projects
  STIP - 5 yr plan

Back to SD DOT
Site Index
Search this Site
Help
Feedback
Contacts




Exit 52
What is being built?
Photos
Feedback
Home
Project Schedule
2009
  • Complete the new westbound lanes of I-90 and open to traffic by the end of July 2009.
      Concrete paving is complete with work continuing on the asphalt shoulder. Westbound lanes of I-90 tentatively scheduled to open to traffic on July 24. 2009.
  • Complete grading and surfacing on SD79 from north Kimberly Drive to south Kimberly Drive.
    • Grading and C&G are completed.
    • Asphalt surfacing is scheduled to be completed by July 29, 2009
  • Complete grading and surfacing on SD79 from Foothills Road (Old Exit 51 on and off ramp) to the Existing Eastbound I-90 bridge over the RR tracks.
    • Grading is complete.
    • Asphalt surfacing is scheduled to be completed by July 31, 2009.
  • Begin construction of the new eastbound lanes of I-90 August 10, 2009.
    • Traffic will be switched to two-way traffic in the newly constructed westbound lanes so the eastbound lanes can be constructed.
    • Eastbound lanes of I-90 scheduled to be completed October 30, 2009.
  • Complete grading and surfacing on SD79 between south Kimberly Drive and Anderson Road.
    • Tentatively scheduled to start on August 17, 2009.
    • Traffic will maintained on a gravel surface and piloted through the construction zone during working hours. During non-working hours one lane of traffic will be open both directions