The overall completion date is November 3, 2008.
Phase I - Starts February 25, 2008 -- Interim Completion date of July 25, 2008
- I-90 traffic preparation work
- Beginning March 8, 2008, traffic will be head to head in the eastbound lanes between Exit 40 and Exit 32
- Grading and realignment work in the westbound lanes
- Extension of the Multiplate structure over the DM&E Railroad
- Reinforced Concrete Box Culvert Extensions
No work on the project during the Sturgis Motorcycle Rally - July 26, 2008 to August 10, 2008
Phase II - Starts August 11, 2008
- I-90 traffic preparation work
- Traffic will be head to head on I-90 in the westbound lanes between the Tilford Weigh Station and Exit 40
- Epoxy chip seal work at Exit 34 bridge in the eastbound lane.
|
|