Bradsky Road Bridge Project Start Delayed
blank space

For Immediate Release:  Wednesday, February 14, 2018

Contact:  Jesse Nelson, SDDOT.  605.390.7978

 

RAPID CITY, S.D. – Corr Construction Services will begin construction on the removal and replacement of the county bridge south of Highway 44 on Bradsky Road in Rapid City on Friday, March 2.

 

Work was originally scheduled to begin Monday, Feb. 26, and has been pushed back due to weather.

 

Work will begin with the construction of a detour road over Rapid Creek immediately to the east of the existing bridge. Following completion of the detour road, the bridge will be removed and replaced with a new structure at the same location.  

 

Traffic will be maintained on Bradsky Road on the detour road until the new bridge is complete.

 

Construction of the new bridge is ex­­­­pected to be complete in June of 2018.

 

For complete road construction information, visit www.safetravelusa.com/sd or dial 511. 

 

- 30 -